Project Update: Phase Two Construction

Beginning the week of January 12, 2026, the City’s contractor will start construction along 25 Road. Work will occur in three rotating phases to minimize traffic impacts, progressing from north to south and ending at the intersection of 25 Road and Patterson Road. During closures, local traffic will be detoured onto nearby residential streets to maintain access to homes, businesses, and schools. Upcoming work will include the installation of additional utility infrastructure along 25 Road.
Map of initial construction along 25 Road

Initial Construction will begin the week of January 12, 2026, through the beginning of February. This includes a road closure from Waite Ave. through F 1/2 Rd. Local traffic will be detoured to Waite Ave. on the north and F 1/2 Rd. or F 1/4 Rd. on the south. During construction, other travelers should use alternate routes along 24 1/2 or 25 1/2 Rd.






















Xcel Energy 25 Road Natural Gas Project 

As of Dec. 13, 2025, Xcel Energy has completed their relocation of a natural gas line as a part of the 25 Road Natural Gas Project in advance of the Four Canyons Parkway Project. View Xcel Energy's website to learn about the completed Natural Gas project. 

Graphic showing the project alignment and phasing of the project.


Phase 1 - Construction Complete

  • Focus is on the section of roadway between 24 and 24 1/2 Road
  • New 4-lane arterial from 24 Road to 24 1/2 Road
  • Signalized intersection at 24 Road
  • Modern Roundabout at 24 1/2 Road

 

Area of streets in Grand Junction representing the phase 1 construction that will occur 2024

Phase 2 - Construction in mid - 2025

  • Focuses on the roadway between 24 1/2 Road to 25 Rd
  • New 4-lane arterial from 24 1/2 Road to 25 Road
  • The reconfigured intersection at 25 Road to improve capacity and safety
  • Reconstruction/widening of 25 Road south to Patterson

Phase 2 construction is expected to be completed by the end of 2026. 

Area of streets in Grand Junction representing the phase 2 construction that will occur 2025

History

In 2005, the F 1/2 Area Corridor Study was completed and included a public involvement process. The findings from the Study provided the foundation for further transportation planning efforts and were incorporated into the adopted 2018 Grand Junction Circulation Plan.   

In 2019, voters approved ballot measure 2A, which provides funding for the F ½ Road Parkway, as well as multiple transportation expansion projects within the City. This 5-lane, multimodal arterial will provide an alternative route around congested Patterson Road and serve a rapidly developing area. 

In 2024, City Council adopted a name change for the F ½ Road Parkway to become Four Canyons Parkway, based on the ability for travelers to view four different canyons from the parkway.

Project Benefits

  • Provide access to adjacent neighborhoods
  • Alleviate traffic congestion
  • Accommodate growth and new development
  • Provide safer access for homes along 25 Road
  • Improve existing utility infrastructure (i.e. storm drain, irrigation)
  • Provide safe routes for pedestrians and cyclists

Project Alignment

The project alignment is from 24 Road to 25 Road along F 1/2 Road. 